|
Structure
of Sector
The
development of Bhutan's energy sector is of
crucial importance to the country, and in
recent years high priority is placed on this
sector. In the past the major source of energy
was fuel-wood which, together with kerosene
and LPG, is still widely used for domestic
purposes, followed by diesel and petrol,
predominantly for transport. Now,
hydroelectric power is assuming the leading
role in the consumption pattern of
energy./p>
Hydroelectric
Power
The
country is endowed with large hydropower
generation potential, the total capacity
estimated at over 20,000 MW. The Power System
Master Plan (PSMP) study conducted during
1990-93, identified 91 hydropower potential
sites above 10 MW capacity. The list of
potential sites is not exhaustive, for many
inaccessible sites were not surveyed by the
study. The 1995 update of the
techno-economically exploitable hydropower
potential is over 16,280 MW.
During
the 7FYP, the power sector accounted for some
25% of government revenue. The annual domestic
consumption of electricity increased from
216.455 GWh at the end of 6FYP to 340.773 GWh
by the middle of 1995. The distribution
network also increased, along with the number
of consumers from 19,626 to 29,000. There are
at present 23 hydroelectric generating
stations with 344 MW installed capacity plus
13MW Diesel Generator sets. The commissioning
of Chukha tail race tunnel and Rangjung Hydro
Power Project during 7FYP added 20 MW to the
overall generation capacity.
National
Power Generation Data during 1990-95 GWh
(million Units)
| Source |
1990-91 |
1991-92 |
1992-93 |
1993-94 |
1994-95 |
| Mini
hydel |
6.619 |
7.364 |
5.046 |
5.488 |
5.880 |
| Micro
hydel |
0.876 |
0.876 |
1.445 |
2.015 |
2.015 |
| Chukha
Hydel |
1542.408 |
1554.37 |
1677.812 |
1679.239 |
1623.31 |
| Diesel
power |
0.046 |
1.315 |
3.059 |
1.085 |
1.069 |
| Total
Generation |
1549.949 |
1563.925 |
1687.362 |
1687.827 |
1632.878 |
Solar
Energy
The
solar power programme was launched to provide
electric light to institutions in the remote
areas. By the end of 7FYP, there were 1316
photovoltaic panels throughout the country
distributed to schools, monasteries, basic
health units and some to remote animal
husbandry farms. With the good sunshine hours
available in Bhutan, this recent and renewable
form of energy has proved to be a viable
alternative to grid supply where it has low
economy of scale.
Fuel
Wood
Fuel-wood
continues to be the main source of energy for
lighting, heating and cooking in the rural
areas. At the national level it accounts for
more than 75% of total energy consumption. It
is estimated that per capita consumption of
firewood is 1.2 ton which is one of the
highest in the world. In order to minimize
wood consumption, extensive rural
electrification was launched in consecutive
five year plans.
Fossil
Fuel (Petroleum products)
With
the development of communications, transport
facilities also expanded rapidly during he
7FYP, thus increasing the consumption of
imported petrol and diesel oil. While the
consumption of kerosene has also increased in
the rural areas for cooking and lighting, LPG
is now in general use for cooking in the urban
areas.
The
import of petroleum products during the period
1991-95 
| Fuel
import |
1991 |
1992 |
1993 |
1994 |
1995 |
| LPG |
-
|
720
ton |
1,800ton |
1,741ton |
1,675
ton |
| Kerosene |
6,253
kL |
7,122
kL |
8,078
kL |
6,691
kL |
7,691kL |
| Diesel |
16,173
kL |
16,778
kL |
16,461
kL |
17,647
kL |
20,035
kL |
| Petrol |
3,574
kL |
3,506
kL |
3,469
kL |
3,530
kL |
3,690
kL |
Finance
As
a result of financial constraints, major
projects such as Kurichu and Basochu
Hydro-electric Projects, transmission grids,
urban electrification and rural
electrification were delayed. These
capital-intensive projects which were expected
to be completed during 7FYP, could not be
launched until the second half of the plan and
completion will therefore take place in 8FYP
Manpower
Most
Power Sector activities are labour-intensive,
and the lack of sufficient labour is a
constraint which often hinders timely
completion and maintenance of projects. In
addition to unskilled and semi-skilled labour,
there is also an acute shortage of skilled
manpower for line maintenance and supervision
in the filed. The Division of Power staff
strength is only 685, inclusive of finance and
administrative personnel, against the
projected requirement of 1411 for 7FYP.
Technical
The
power sector with its large establishment and
distribution network is faced with an acute
shortage of transport. The Department also
lacks sufficient tools and plants for proper
maintenance of the existing system, and
portable communication sets to coordinate
simultaneous activities in the field between
two or three groups working on the same line.
|
INSTITUTIONS

|
Hydropower
The
division of Power, is responsible for
coordinating activities related to hydropower
generation and distribution, and is also the
main central agency for power generation and
distribution from small hydels. Altogether,
under its Operation and Maintenance and
Project Wings, it controls 20 hydel units and
coordinates the activities of 7 decentralized
Electricity Supply Units.
The
Chukha Hydro Power Corporation (CHPC) is an
autonomous body under a Board of Directors.
Similarly, Kurichu Project Authority (KPA) is
overseeing the general administration and
overall coordination of Kurichu Hydropower
Project activities under the guidance of the
Board of Directors.
Fuel
Wood
The
Division of Forest, Ministry of Agriculture,
regulates the fuel wood supply. In the rural
areas fuel wood from dead wood is free but
cutting of live trees is regulated by permit
issued by the local Dzongkhag Forest Ranger.
In the urban areas fuel wood is supplied by
licensed contractors and to a certain extent
by the registered saw mills.
Fossil
Fuel
Two
private companies supply petroleum fuel
products in the kingdom. There are 24 fuel
depots situated at convenient point in various
dzongkhags. The Ministry of Trade and
Industries regulates the price and supply of
fossil fuels.
|
REVIEW
OF PAST PERFORMANCE
|
Objectives
of the 7FYP
-
Increase Government revenues through the
generation of power for sale to India and to
domestic industries;
- Fulfil demand for electrical energy at
minimum cost, and as far as possible on a
uniform basis, to all the consumers through a
safe reliable and efficient distribution
system;
- Ensure balanced regional growth through the
provision of energy for industrial
development; and
- Ensure environmentally sustainable use of
hydropower resources.
Strategies
-
Coordinate efforts with other sectors in
protecting water resource catchments;
- Ensure environment friendly, and safe
construction of hydropower generation,
transmission and distribution infrastructure,
including rural electrification;
- Mitigate the shortage of manpower by HRD as
well as by contracting more work to the
private sector.
|
ACHIEVEMENTS

|
Power
Generation Programme
The
construction and commissioning of the 2.2 MW
Rangjung hydel Project was completed. The
plant is in operation and providing additional
electricity to the distribution network for
urban and rural electrification in Trashigang
and Yangtse Dzongkhags. It covers 7 gewogs and
give electricity to more than 3,000 consumers
(households).
Kurichu
Project (45 MW) was only about 40% completed,
and about 20% in the case of Basochu
Hydropower Project (60.8 MW). These two
projects will be commissioned during the 8FYP.
Transmission
Programme
The
construction of 40/20 MVA, 220/66/11 kV
substation at Semtokha and 50/20 MVA,
132/66/11 kV substation at Gelephu under
Government of India grant assistance was
completed. The construction of a 20 km 66 kV
line between Lobesa and Basochu was
implemented and is expected to be completed by
the beginning of 8FYP. This line will provide
the construction power to Basochu Hydropower
Project initially, and later on evacuate power
from Basochu stage I (22.2 MW) to feed into
the existing grid at Lobesa.
The
feasibility study for the construction of 35
km 220 kV line between Basochu and Semtokha
substation was also completed. Grant
assistance from the Government of Japan is
expected for the construction of this 220 kV
line and its substation bays. It would be
commissioned with 8FYP in parallel to the
commissioning of Basochu stage II.
On
the Eastern and South-Eastern grids the
walk-on survey of transmission lines and
substations was completed in 1993-94, and with
Government of India funding these transmission
line swill be completed in the 8FYP.
Urban
Electrification and Sub-transmission &
Distribution Programme
In
Thimphu numerous substation & underground
cable upgrading was carried out to meet the
growing demand for power. the construction of
a dedicated 11 kV line between Gelephu &
Sarpang, and 33 kV line between Gomtu &
Samste, to meet the growing demand in these
two Dzongkhags was completed.
The
sub-transmission and distribution programme
funded by the Government of India for the 6
Dzongkhags (Ha, Paro, Trashigang, Pemagatshel,
Lhuntse and Samdrup Jongkhar) was completed by
the end of 7FYP. This programme brings
electricity to Pemagatshel. Lhuntse
sub-transmission & distribution network
was upgraded and improved to receive power
from the proposed Ganzur micro hydel which is
to be upgraded to 70 kW capacity.
A
total of 46 sets of solar panels were also
distributed to public institutions in Gasa
Dzongkhag where there is no electricity.
Rural
Electrification Programme
The
rural electrification scheme achieved over 80%
of its target in the 7FYP despite financial
delays. By the end of the plan the
electrification of 107 villages was undertaken
from internal resources, plus a further 47
villages with grant assistance from the
Government of India and from the Dutch
Government under the Sustainable Development
Programme. 5,990 rural households received
electricity during this plan period. The
programme for the remaining villages will be
completed in 8FYP.
Hydropower
/investigation and Feasibility Study
The
spill-over works of the Power System Master
Plan from the 6FYP were completed in 1993. The
National Hydrological and Meteorological
networks were established with trained
manpower. The Pre-feasibility study of four
hydropower project sites was carried out, and
Detailed Project Reports (DPR) for Tala (1020
MW), Wangchu (900 MW), Bunakha (180 MW) and
Sankosh (4060 MW) projects were prepared.
Investigation of Gyetsa pondage scheme to
augment the peaking power in Bumthang was also
completed by the end of the 7FYP.
Unspecified
Schemes
During
the 7FYP, a number of unspecified schemes were
implemented, including rehabilitation of mini
hydels of Thimphu, Chenary in Trashigang and
Gangzur in Lhuntse to produce original rated
capacity. An additional tail race tunnel at
the cost of Nu 33.540 million was constructed
in order to generate 18 MW more from CHPC.
Further, a Small Transformer Production (STP)
project was implemented in collaboration with
Interlife/PMU of Sweden to manufacture small
transformers within the range of 16 kVA to 125
kVA in the country.
|
OBJECTIVES
AND STRATEGIES FOR THE 8FYP

|
Objectives
-
Implement construction, selectively, of power
projects for which detailed project reports
have been completed;
- Enhance revenue collection by efficient
operation of the existing hydropower stations
and its distribution system;
- Encourage the use of energy sources like
hydropower which are renewable,
environmentally clean and sustainable;
- Extend rural electrification;
- Liaise with other government agencies to
ensure the protection of existing and future
hydropower catchment areas.
- Develop policy guidelines and power tariffs
conducive to the promotion of bilateral and
multilateral cooperation in hydropower
development.
Programmes
for 8FYP
The
programmes are to be implemented at National
and Dzongkhag levels. The National level
programmes are: Power generation construction
and transmission, feasibility studies of new
projects, alternative energy, research &
development and institutional development. The
Dzongkhag level programmes consist of urban
and rural electrification in the respective
Dzongkhags.
Power
Generation (Construction) Programme
This
programme includes the major investment
projects for the 8FYP which will be reflected
outside the development plan outlay. These
projects are :
Kurichu
Hydroelectric Project (45 MW) and Basochhu
Hydroelectric Project (60.8 MW), will be
commissioned around the middle of 8FYP. The
Kurichu Hydroelectric project will provide 45
MW of power, 322 GWh of energy, in the Eastern
part of the country, facilitating economic
activity in the 5 Eastern Dzongkhags, as well
as the construction of Dungsum Cement Project
at Nanglam. On completion, the Bascochu
project will produce 291 GWh of energy and
feed the existing Western transmission grid
being supplied by Chukha Hydro Power
Corporation, thereby increasing the
reliability of power supply to ten Dzongkhags
in the western pat of the country.
The
Detailed Project Report (DPR) of Tala
hydroelectric Project (1020 MW) was preapred
in 1994 and the agreement for financing, power
purchase and project implementation was
subsequently signed with the government of
India in 1996 during His Majesty's visit. It
is envisaged that the pre-construction and
infrastructure development activities will
commence on the eve of the 8FYP, with
construction extending beyond 8FYP and
commissioning around the middle of the 9 FYP.
This project will generate 3962 GWh of energy
per annum and will be one of the biggest power
plants in the country.
The
Bunakha Reservoir scheme (180 MW) project is
also ready for implementation in 8 FYP, with
commissioning in 9 FYP. According to the
Detailed Project Report, it will generate 688
GWh annual production (90% dependable year)
and contribute 101 GWh of additional energy to
the existing Chukha hydel project and further
cascade effect on the Tala project.
While
the above mega projects are designed mainly
for export, two small hydro power projects -
Lhuntse Small Hydel Project (1 MW) and Panbang
Mini Hydel Project (200 kW), will also be
constructed during the 8FYP for local domestic
supply and distribution to neighbouring
Dzongkhags.
|
POWER
TRANSMISION LINE PROGRAMME

|
New
Lines & Substations
Construction
will include a 220 kV line from Basochhu to
Semtokha and a 66 kV line from Basochhu to
Tsirang and diversion to Dagana. Similarly,
under the Eastern grid plan, for evacuation of
Kurichu power, a 132 kV transmission line from
Gyelposhing to nanglam, and a 66 kV line form
Gyelposhing to Nanglam, and a 66 kV line from
Gyelposhing to Transhigang via Mongar and
Pemagatsel to Deothang, are to be constructed.
A walk-on survey for the eastern grid as well
as the south-central grid has been conducted.
Successful implementation of these
transmission networks, especially the eastern
grid will provide much needed power in this
densely populated part of the country.
Improvement
& Upgrading of Transmission Lines &
Sub-stations
-
One third of the 66 kV transmission line
towards Gomtu and Samtse is in a land slide
zone and many towers are liable to be washed
away during heavy rains. At least 10 km of the
27 km line will therefore be realigned. The
66/1 kV sub-station at Gomtu is likely to
reach its capacity after the upgrading of
production capacity of PCAL. More over, the
power supply to Samtse and the surrounding
villages need to be carried over the 33 kV
line. Accordingly, it is proposed to install
one 5 MVA, 66/33 kV transformer and
substation.
- The existing 6 MVA 66/33/11 kV will be
adequate to meet the demand for Gedu as it is
an industrial area and selected site for
headquarters of Tala Project during
construction. It will therefore be upgraded to
a 20 MVA, 66/33 kV substation.
- Under Phuntsholing Electricity Supply Unit,
the Singyegaon 6MVA, 66/11kV substation will
be upgraded to 10 MVA, 66/33/11 kV in order to
meet the growing demand from the mushrooming
small industries at Pasakha and to electrify
the villages in Bhalujora Gewog. Similarly the
existing 6 MVA sub-station for distribution in
Phuntsholing town is to be augmented with
another 10 MVA transformer to meet the
increasing demand for power in the urban area.
- The tripping of line and snapping of
conductors at high altitude and during
snowfalls interrupt power supply when it is
most required. As a remedy it is proposed to
install snow-rings for transmission lines
passing through the snow zone, which will
prevent snow flakes accumulating on the
conductors. A few troublesome transmission
towers will also be relocated in order to
minimize maintenance work.
Power
Distribution Programmes in Each Dzongkhag
The
implementation of the Power Distribution
Programme will be carried out t the Dzongkhag
level because the distribution of electricity
is delegated to the Electricity Supply Unit (ESU)
of each Dzongkhag. The programme has the
following schemes:
Rural
Electrification Scheme
It
was not possible to complete all the rural
electrification schemes planned for 7FYP, so
that some are carried over to 8FYP. These will
be consolidated into the 8FYP rural
electrification scheme based on proposals from
the Dzongkhag GYT's and DYT's and availability
of generation capacity. The scheme will
include grid extension, the constructing of
micro/mini hydels and, in some cases, the
provision of photovoltaic panels, and,
overall, provide electricity to 5000 rural
households.
Urban
Electrification Scheme
Taking
account of Dzongkhag plans for township
development, new sub-transmission and
distribution networks will provide electricity
to 1500 new consumers in these urban areas.
The scheme will be implemented through grid
extension where electricity is available now,
and will involve construction of a 33/11 kV
sub-transmission line and 440/230 volts
distribution lines & substations with
matching maintenance centers.
Improvement
of Existing Supply in Rural and Urban Areas
This
scheme will focus on the improvement of
efficiency, voltage regulation and quality of
the existing Electricity Supply Services (loss
reduction, reliability improvement, energy
conservation) by system upgrading, systematic
maintenance and replacement of old parts,
including existing photovoltaic panels. The
scheme will also augment the existing network
by adding new lines and substations.
Hydropower
Feasibility Studies
Feasibility
studies on the following major hydropower
projects will be undertaken during the 8FYP:
- Wangduephodrang Hydro Power Project stage I
(site 3.120) - 760 MW Punatsangchhu below Jala
/ Ula villages.
- Wangdiphodarang hydro Power Project stage II
(site 3.230 B) - 650 MW below Daga Uma
village.
- Mangdechu Hydro Power Project (site 4.020) -
265 MW near Kunga Rabten
Institutional
Development
The
increasingly important role that the power
sector will play in the future of the country
and its economy, will inevitably give rise to
substantial opportunities for employment.
Accordingly it is proposed to prepare a
long-term HRD master plan for the power
sector, and to establish a power Training
Institute during * FYP, for the construction
of which the Government of India has already
committed the funds.
Other
Programmes
Apart
from the above major programmes, a number of
miscellaneous studies and research activities
will be carried out related to the long-term
development and sustainability of the sector.
Financial
and Manpower Requirement 
| |
1997/98 |
1998/99 |
1999/00 |
2000/01 |
2001/02 |
Total |
| 1.
Capital |
590.717 |
990.539 |
671.357 |
514.551 |
293.643 |
3060.807 |
| 2.
Recurrent |
142.000 |
172.000 |
184.000 |
190.000 |
209.000 |
896.000 |
| 3.
Total |
732.717 |
1162.539 |
855.357 |
704.551 |
502.643 |
3956.807 |
| 4.
Manpower |
41 |
45 |
43 |
41 |
41 |
211 |
| 5.
TA (mm) |
-
|
-
|
10 |
-
|
-
|
10 |
PROJECT PW 01 :
LHUNTSE SMALL HYDEL PROJECT
Project
summary :
1.
Sector : Power
2.
Location : Wangla / Yongla Chu, Lhuntse
3.
Executing Agency : Division of Power, MTI
4.
Implementing Agency : Projects &
Investigation Wing Division of Power
5.
Estimated cost:
Recurrent : Nu. 8.400 m
Capital: Nu. 105.000 m
Total: Nu 113.400 m
6.
Funds Secured : Nil
7.
Financing Gap: Nu. 105.000 m
8.
External finance reqd.: Nu. 105.000 m
9.
Status : New
10.
Documents available: Pre-feasibility study
reports (1996) by CWC.
Project
Objectives
Generate
hydro-electricity for meeting the most
essential electricity demand of Lhuntse
district. The villages in and around Khoma
village, Lhuntse town and Tangmachu areas are
planned to be electrified by the power
supplied from this project.
Project
Description
Lhuntse
Small Hydel project of 1 MW capacity is bu9ilt
by tapping the water from Wanglachu river near
Khoma village. The project is expected to
generate 8.76 GWh of energy annually at 60%
plant use factor. The project site lies about
8 km away from the main road. It is a
run-of-the river scheme. Cableways will be
used for transport of materials.
Project
Impact
The
project is expected to benefit more than 1000
numbers of household consumers and about 3
boarding schools, 1 hospital, 2 Basic Health
Units, telephone exchange and other Government
institutions including Lhuntse town. Some
small scale agro-based industries may also
come up and promote industrial utilization of
power. The project is designed in such a way
that it will have minimum negative
environmental impact. On the contrary, it will
reduce fuel wood consumption and save forest
to some extent. The project will provide an
alternative energy source for domestic
consumption and reduce pressure on fuel wood
which is already very scarce.
Project
Management
The
Projects and Investigation wing of the
Division of Power will manage the project
construction activities in cooperation with
Lhuntse Dzongkhag Administration.
Financing
Detail 
Financing
and construction details are as follows :
| Annual
Outlay |
1998-
99 |
1999-
00 |
2000-
01 |
Total |
| Capital |
35 |
35 |
35 |
105 |
| Recurrent |
2.8 |
2.8 |
2.8 |
8.4 |
| Total |
|
37.8 |
37.8 |
113.4 |
Manpower
Requirement
It
is expected to mobilize more than 252
personnel, both skilled and unskilled,
regularly at the site for 3 years of
construction period. Local labourers will be
employed to the extent possible with import of
a few skilled labourers and technicians.
Equipment
Electro-mechanical
equipment and technology will be imported from
India or other countries.
Technical
Assistance
Professional
services for the detailed design, construction
supervision and for final testing and
commissioning of plants and equipment of
hydropower project will be required.
PROJECT
PW 09 : SOLAR ENERGY PROJECT
Project
summary :
1.
Sector : Power
2.
Location : Nationwide
3.
Executing Agency : Division of Power, MTI
4.
Implementing Agency : Renewable Energy Unit,
Division of Power
5.
Estimated cost:
Recurrent : 2.800 m
Capital: Nu. 35.000 m
Total: Nu . 37.800 m
6.
Funds Secured : Nil
7.
Financing Gap: Nu. 35.000 m
8.
External finance reqd.: Nu. 35.000 m
9.
Status : Continuation
10.
Documents available: None
Project
Objectives
Implemented
solar energy programme by installation of
photovoltaic panesl, solar water heaters and
solar dryers.
Project
Description 
The
Solar Energy Programme is aimed at providing
alternative sources of energy supply for
lighting, heating of water in the remote and
rural areas where electricity grid extension
or micro hydropower generation is not
feasible/possible during the next 25 years.
Besides, the solar water heating or air drying
systems can be an effective means of utilizing
solar energy in conservation of other energy
options. It can supplement or augment the
supply of other forms of energy. Photovaltaic
lighting will be locally fabricated or
assembled. The remote boarding schools, Basic
Health Units, monasteries and remote
households will be the target beneficiaries.
As the life of lighting sets, charge
controllers and batteries is only 5 years,
maintenance strategy for sustaining the system
will be worked out and given to the end-user
for their follow-up.
Project
Impact
The
socii-economic condition of the propel will be
improved with the provision of the energy
facilities such as solar lighting, heating or
drying devices. Pre-heated water from solar
water heaters can be used for cooking foods,
thereby saving extra heating energy normally
provided by fire-wood or other forms of energy
(gas, kerosine). Photovoltaic panels can
provide light to replace kerosine lamps or
wood-splinters. Solar dryer can be effectively
used to dry chilies (peppers), fruits or meat
in a hygienic manner. Thus solar energy will
provide alternative options of renewable
energy to the consumers and help to reduce the
fire-wood and kerosine consumption etc. to
minimize global warming effect and to reduce
pollution.
Project
Management
The
Renewable Energy Unit of the Division of Power
will implement the project with a little
support from the consultant. The Central
Maintenance Unit will provide the prototype
testing and fabrication facilities for the
development of prototypes. Once the designs
are proved and found adaptable at site, they
will be patented and given to private
entrepreneurs for mass fabrication and
marketing. Similarly PV panels will be
installed and, maintained through private
service sectors.
Financing
Detail
The
project will involve the installation of 500
solar lighting sets, 25 water heating systems,
10 solar dryers besides maintenance of the
existing PV panels over the 8FYP period as
pilot schemes.
The
breakdown of costs is as follows:
| No. |
Name
of activity |
Unit |
Qty |
Rate |
Amount |
| 1. |
Maintenance
of existing PV system and making the
system sustainable |
sets |
500 |
0.01 |
5.0 |
| 2. |
Purchase
and installation of solar electric
lights and spares |
sets |
500 |
0.04 |
20 |
| 3. |
Prototype
design and fabrication and
installation of solar water heating
systems. |
sets |
25 |
0.25 |
6.25 |
| 4. |
Prototype
design and fabrication of solar dryers |
sets |
10 |
.10 |
1.0 |
| 5. |
Professional
services |
lot |
|
|
2.75 |
| |
Total
capital costs |
|
|
|
35.00 |
| |
Total
recurrent costs |
|
|
|
2.8 |
Manpower
Requirement
The
project will be implemented through private
parties under the technical guidance of Rural
Energy Unit, Division of Power. About 26
(engineers and technicians) are required on a
regular basis to implement the project.
Equipment
Photovoltaic
panel and batteries will be imported. Only
materials will be imported for the
assembly/fabrication of other items such as
solar water heaters, invertors, fixtures and
solar dryers.
Technical
Assistance
Technical
assistance is required for funding part of the
project.
PROJECT
PW 03 : WESTERN TRANSMISSION GRID
Project
summary : 
1.
Sector : Power
2.
Location : Chukha, Thimpu, W/Phodrang, Tsirang
& Daga
3.
Executing Agency : Division of Power, MTI
4.
Implementing Agency : Transmission Const.
Unit, West
5.
Estimated cost:
Recurrent : Nu. 39.80 m
Capital: Nu. 497.50 m
Total: Nu 537.30 m
6.
Funds Secured : Nil
7.
Financing Gap: Nu. 537.30 m
8.
External finance reqd.: Nu. 537.30 m
9.
Status : New
10.
Documents available: 1] Power System
Development Study Report - 1995, Worley
Consultant, TA 2043-BHU, ADB;
2] Detailed Project Report of Tala
Hydro-electric Project, August 1993. WAPCOS;
3] 7FYP Document Vol. 1 and Vol. 2, 1991.
Project
Objectives
Transmit
hydro-electricity generated from Chukha,
Basochu, Tala Punatsangchu hydro-electric
projects to the various load centres in the
western region of the country and to export
surplus power to India.
Project
Description
The
following transmission lines and substations
will form the part of Western grid to be
expanded during the 8FYP and 9FYP. The
sub-projects will comprise the following
schemes:
Transmission
|